What Is the Plan for Supertech's Stalled Projects?
NBCC is currently finalising tender documents for the 16 projects. The committee has proposed 27 or more separate sub-tender packages to execute the construction work.
A tender for the Supertech River Crest project in Rudrapur had already been floated on September 16, according to the report.
The committee has also said that the required project sites will be made available for the planned construction work.
However, funding remains one of the major challenges in restarting the projects. The committee is exploring interim finance as well as alternative funding options through publicsector banks and financial institutions.
Funding Remains a Key Challenge
The committee received financing proposals from two investment and capital firms, but these were not considered viable because of the interest rates offered.
It has therefore approached public-sector banks for financing on more suitable terms. The banks have requested a Techno-Economic Viability (TEV) report before evaluating the funding proposals.
The report is expected to be completed by December 15, 2026.
Another potential source of funding is the sale of unsold project inventory. The committee has asked a global accounting and professional services firm to verify the unsold inventory figures.
How Many Units Are Involved?
According to an NCLAT order dated December 12, 2024, the 16 projects had a total of 50,356 units.
Of these:
40,316 units had already been sold.
10,040 units remained unsold.
This makes the construction-revival process particularly important for existing homebuyers who have been waiting for their projects to progress.
Which Supertech Projects Are Covered?
The 16 projects are spread across Uttar Pradesh, Uttarakhand and Bengaluru.
They include:
Noida: Capetown, Romano, Eco-citi and Northeye
Greater Noida: Eco-Village 1, Eco-Village 2, Eco-Village 3, Sports Village and Czar Suites
Other projects are located along the Yamuna Expressway, Gurugram, Meerut, Rudrapur, Bengaluru and Dehradun.
What Happens Next?
The immediate focus is on completing the tendering and financing process.
The proposed timeline includes:
October 1–15, 2026: Tenders to be issued in phases
↓
December 15, 2026: TEV report expected
↓
January 16, 2027: Targeted commencement of construction
The actual progress will depend on completion of the tendering process, availability of funding and other project-level requirements.
The Supreme Court had earlier approved NBCC's takeover of the 16 Supertech projects in February 2026. The broader question of whether NBCC should take over all 30 Supertech projects remains under consideration before NCLAT.
Key Takeaways
Construction of 16 stalled Supertech projects is targeted to begin on January 16, 2027.
NBCC is preparing tender documents for the projects.
27 or more sub-tender packages are proposed.
Funding remains a significant challenge for the revival process.
A TEV report is expected by December 15, 2026.
The 16 projects include developments in Noida, Greater Noida, Uttar Pradesh, Uttarakhand and Bengaluru.
The projects collectively involve more than 50,000 housing units, according to the cited NCLAT order.
Frequently Asked Questions
When will construction start on the stalled Supertech projects?
Construction is targeted to begin from January 16, 2027, according to the Supreme Court appointed committee's latest plan.
How many Supertech projects are being revived?
The current plan covers 16 stalled Supertech projects under the NBCC-led implementation process.
What is NBCC's role in the Supertech projects?
NBCC is working as the project management consultant and is preparing the tendering and implementation process for the projects.
Why were the Supertech projects delayed?
The projects have faced a combination of financial difficulties, insolvency proceedings and legal/implementation hurdles. Funding continues to be a key issue in the revival process.
Which areas have Supertech projects covered under the plan?
The projects are located across Uttar Pradesh, Uttarakhand and Bengaluru, including several projects in Noida and Greater Noida.
How many units are involved in these projects?
The 16 projects had 50,356 units, of which 40,316 had been sold and 10,040 remained unsold, according to the NCLAT.
Written by: Kuldeep
Source: Hindustan Times